Infrastructural Development

Buildings

S.N. Name of Building Source of Funding Stage (Complete) Stage (Inomplete)
1 Administrative Building ICAR Completion Year : 1999
Plinth area (Sq.m) : 616.86
Expenditure (Rs.) : 20.70
Starting Date :
Plinth area (Sq.m) :
Status of construction : completed
2 Farmers Hostel ICAR Completion Year : 2003
Plinth area (Sq.m) : 310.68
Expenditure (Rs.) : 18.00
Starting Date :
Plinth area (Sq.m) :
Status of construction : completed
3 Staff Quarters (6) ICAR Completion Year : 2008
Plinth area (Sq.m) :
Expenditure (Rs.) : 26.05
Starting Date :
Plinth area (Sq.m) : 400.00
Status of construction : completed
4 Demonstration Units (2) ICAR Completion Year : 1999
Plinth area (Sq.m) :470.15
Expenditure (Rs.) : 3.00
Starting Date :
Plinth area (Sq.m) :
Status of construction :
5 Fencing ICAR Completion Year : 2008
Plinth area (Sq.m) : 2100 Metre
Expenditure (Rs.) : 16.12
Starting Date :
Plinth area (Sq.m) :
Status of construction : 75% work is completed

 

Vehicles

Vehicle Year of Purchase Cost (Rs.) Total kms. Run Present Status
Bolero # # # #
Tractor # # # #
Motor Cycle # # # #

 

Equipments & AV Aids

S.N. Name of the equipment Year of purchase Cost (Rs.) Present Status
1 Computer with Accessories # 48,678 Not in Working
2 Xerox Machine # # #